Substation “RAVSHAN” 220/110/10 kV
The reconstruction project of the substation “Ravshan” 220/110/35/10 kV financed by the Islamic Development Bank (IDB Loan 0054-TJK/ICB-01) was carried out by OJSCTGEM.
Project consultant: MVV Decon
Work performed:
● Supply, installation and commissioning of a new 220/110/10kV, 125 MVA AT
● Installation of a new 25 MVA 10kV/35kV boost transformer
● Installation of 3 new 220 kV SF6 circuitbreakers
● Installation of 1 new inductive voltage transformer
● Installation of 2 new capacitive voltage transformers
● Installation of 2 new 220 kV line traps
● Construction of a new control building;