In 2013, the company completed the design and power supply of the Zarnisor mine locatedin Matcho district of the Republic of Tajikistan.

Work performed:

Supply and installation of equipment, installation of poles for 110kV transmission lines, wires, power cables and installation of 25 MVA 110/10kV transformer.

Project duration period:

11/20/2012– 10/31/2013