Inspection of the progress of construction works at "Sebzor" HPP
The Founder of Peace and National Unity - Leader of the Nation, President of the Republic of Tajikistan, Honorable Emomali Rahmon, became familiar with the progress of construction works at "Sebzor" hydropower plant in Roshtkala district.
Honorable Head of State Emomali Rahmon was informed that after the completion of construction works and installation of electronic equipment in the construction of the 110-kilovolt substation of the "Sebzor" hydroelectric power station, with the involvement of specialists from domestic companies - "TGEM" OJSC and "Madad" LLCs, Shahdara river of Roshtkala district was blocked and water was released through a temporary water channel.
After changing the course of the river, construction works on the main dam of the power plant began.
The main dam of the power plant will be built with a length of 60 meters and a height of 8 meters, and its water capacity will be 5 million cubic meters.
Construction materials, including cement and fittings, are available from Dushanbe.
The workers of "TGEM" OJSC have organized a concrete production workshop here for regular activity. At the construction site, the construction of a sand and gravel production plant is nearing completion.
According to experts, the construction of the power plant in this area is not unreasonable, because the speed of water movement here is relatively fast, it does not freeze in winter, and it is very suitable for moving units.
The implementation of the HPP construction project began in December 2020, and it consists of three units.
"Sebzor" HPP will be built with a capacity of 11 MW, and in total, up to 300 people will be employed during the construction of this facility.